Subject: BP PT Plan, Status of Spec, and URL


Business Process Project Team

ebXML Steering Committee, and

Ann Bullen: Marketing and Awareness Project Team,

Please find below the BP PT revised milestones and work plan as well as the BP PT URL for the BP PT Technical Specification. If you have any questions or comments regarding this email, please contact me at 818-706-3882 or marcia.mclure@mmiec.com.

Marcia

Co-lead BP PT

ebXML Business Process Project Team

Milestones and Work Plan

Revised 6/7/00

May 26 Submit first draft BP Technical Specification to full ebXML Work Group for review and comment

        June 5 BP Conference Call 9am PCT

        Team Assignments:

  • Request confirmation from ebXML Steering Committee that the BP PT Technical Specification is still on track for a vote at the August plenary meeting.
  • Karsten: send Bob the demo-case collaboration diagram to further illustrate the metamodel.
  • Brian: revise descriptions based on the latest ebXML descriptions and forward them again to ebXML after internal review.
  • Karsten: forward Comment/Resolution Spread Sheet for posting and tracking issues and resolution
  • Bob: provide collaboration diagrams for the auto example in time for Brian’s 20 June meeting with the CC PT members;
  • Brian: distribute a CC PT writeup of a "context" example from the Brussels meeting.
  • Paul: collect comments until official editor is declared
  • Marcia: include the activities of demonstration by example and collaboration with the CC PT, as identified above, in the Work Plan along with the critical dates relative to the BP Modeling Specification.
  • All Team: Review BP PT Spec on the BP PT website; ID PT members to map BP PT meta-model to existing frameworks; ID Editors; contact Jim Clark to relay the importance of his participation in BP PT.

    June 9 Close of 1st Comment Period June 19 BP

    June 19 Conference Call 9am PCT

    June 20 Team Member Assignment: Brian will meet with Core

Component representatives Arofan Gregory and Sue

Probert to determine the CC PT meta-model status and

fit within the BP PT meta-model.

    June 23 Submit BP PT Approved Technical Specification Revision and log of comment disposition to full

ebXML Work Group

    July 3 BP Conference Call 9am PCT

    July 7 Close of 2nd Comment Period

    July 16-17 ebXML BP Project Team Interim Meeting

    Minneapolis-Minneapolis: work the BP technical specification

    July 21 Submit BP PT Approved Technical Specification Final Revision and log of comments disposition to   full ebXML Work Group

    July 31 BP Conference Call 9am PCT

 

    August 7-11   ebXML San Francisco Plenary Meeting

    November     ebXML Tokyo Plenary Meeting

    February 5-9 ebXML Vancouver Plenary Meeting

    May 7-11        ebXML Vienna Plenary Meeting

If there are any additions or corrections to the BP PT Work Plan, please send to marcia.mclure@mmiec.com. Thank you.

 

Issue: Is the BP PT Technical Specification still considered on track for the "ebXML Plenary Vote" option in August given the difficulty experienced in posting the specification to the ebXML website ?

The answer is "yes."

See ebXML Steering Committee e-mail responses below:

6/5/00 Klaus writes:

It has been over a week now that I have sent on behalf of the BP
and Architecture team their draft specification in pdf form to
Brent. However, they are not shown under on our web site under
"Drafts - Open for Comments".

6/7/00 In response to the BP PT question related to "on track" BPPT Technical Specification, Klaus writes:
In order to overcome the missing links under the "Drafts:
Open for Comment" page for the Architecture, BP and Core
Component Draft Specification, Klaus will post the links on
the ebXML (General) list. The StC agreed not to change the timetable because of the problems with the links being made public outside their
list members.

The BP PT URL to view the specification is identified below:

www.ebxml.org/working/project_teams/business_process/ebxmlspecdoc.zip

 

Marcia McLure

Co-Lead BP PT

 